Assignment #2A
Acme Pharmaceuticals
Apache Facility Expansion (Part A)

Background:
During the First Quarter 2000, Acme Pharmaceuticals, Inc. planned an expansion of their Apache facility. The expansion was to occur during 2000 with the plant to be on-line early December 2000. The expansion was placed on hold during the Second Quarter 2000.

The project has been reactivated and is scheduled to start Monday, Oct. 3, 2005.

A quick series of phone calls confirmed that all original vendors are (a) still in business and (b) interested in rebidding the project.

For cost estimation purposes, assume across-the-board cost increases of 11.75%.

Final costs and vendors will be provided in Assignment #3.

Given:
Materials from the previous project planning effort consisting of
Task:
Construct, print (plot), and present a tentative schedule for the project with a start date of Monday, Oct. 3, 2005. The initial schedule should include only those tasks that were identified in the original project.

Note: You may add summary &/or milestone "tasks" as desired including strategically placed meetings or reviews.